Routine works, gate safety, stairway restoration
RoadsOther
Gate safety and stairway renovation works in the 16th district.
The project repairs and secures existing fences. Includes outdoor stairway renovation to ensure better pedestrian flow.
Voted budget
201k €
Fiscal year
2022
District
16th
Chapter
Final amount & cost overrun — not publicly available at this stage. Administrative accounts publish the voted budget but not systematically the end-of-project balance or amendments. On our roadmap.
Identified companiesauto match ⓘ
These public contracts appear to contribute to this project. This match is automatic and may contain errors — always check the contract object.
FONDERIES DECHAUMONT6 €M
Acbc Fournitur Fonte Voirie Panneaux Grilles Arbres lot 1
Confirmed· 2023
TERSEN800 k €
Lot 3 Deconstruct. pour Mesures Sécurité Batimentaire
Confirmed· 2022
SPIE FACILITIES400 k €
Maintenance Equipts Sécurité des Stations Assainn lot 2
Confirmed· 2022
AXALAN70 k €
Travaux Cloisemment Sécurité Locaux Tech Piscine Berlioux
Confirmed· 2022
ARTELIA56 k €
Etude Sécurité Voies Reservees JOP Tunnel Cours la Reine
Confirmed· 2022
Location
Arrondissement 16 · View on OpenStreetMap ↗
Source
- CA appendix 2022
- Source PDF · page 48 ↗
- Internal ID
- 2022_16_48_007
- Extraction confidence
- 70 %