Nursery School Roquepine - Both schoolyards upgraded
Other
Voted budget
136k €
Fiscal year
2022
District
8th
Chapter
Final amount & cost overrun — not publicly available at this stage. Administrative accounts publish the voted budget but not systematically the end-of-project balance or amendments. On our roadmap.
Identified companiesauto match ⓘ
These public contracts appear to contribute to this project. This match is automatic and may contain errors — always check the contract object.
ASTEN488 k €
Travaux Modernisation 2 Cours EM 16 RUE Roquepine Paris 8E
Confirmed· 2021
ASTEN405 k €
Réfection Cours Oasis EM Domremy 13e
Probable· 2022
COCHERY ILE DE FRANCE376 k €
Travaux Transformation Cours en Cours Oasis EE 32-34 Bruxelles
Probable· 2022
EIFFAGE ROUTE ILE DE FRANCE348 k €
Travaux de voirie et réseaux pour l'aménagement de deux cours
Confirmed· 2024· 5 bids received· Travaux· Travaux construction· Paris
MODULOBASE55 k €
Installation de deux blocs sanitaires préfabriqués dans une cour.
Confirmed· 2024· 1 bid received· Travaux· Travaux construction· Paris
Location
3 Rue Roquépine 75008 Paris · View on OpenStreetMap ↗
Source
- CA appendix 2022
- Source PDF · page 21 ↗
- Internal ID
- 2022_08_21_001
- Extraction confidence
- 70 %